Welcome to the Times Square Alliance Website

Accessibility Navigation:

Masthead_TimesSquare Transformation2

Please check here for ongoing updates from the Times Square Alliance, Con Edison, and the NYC Department of Transportation. For any construction questions, please contact Karen Flores, Community Construction Liaison, directly at (212) 784-0184 at timessquareccl@gmail.com.


**ADVISORY** Water main work continues on 7th Ave. between W. 42nd and W. 43rd St. On/about Wednesday, September 3 and Thursday, September 4, DDC will replace the existing 12" water main pipe at the above mentioned location. In order to replace the pipe, the contractor will schedule a water service interruption. The water shut down will begin at 10:00 p.m. and last for approximately 8 (eight) hours. Water will be restored at the end of the work night. Three lanes of southbound traffic will be maintained.

**ADVISORY** On Monday night, July 14, starting at approximately 10:00 pm, the New York City Department of Design and Construction's contractor will close two lanes of vehicular traffic, on the north side of W. 43rd St. between Broadway and 7th Ave., to continue excavation of the roadway in preparation for the installation of pavers. The south side lane will be open to traffic. The closure will continue 24/7 for approximately six weeks.


Day work, Monday-Friday, 7 am-3:30 pm 

LOCATION

WORK

IMPACT

W. 43rd St. between Broadway & 7th Ave. (north side)

Install Additional Conduit

Pedestrian/building access will be maintained.

Broadway between W. 44th St. & W. 45th St.

Grade & Place Base Concrete; Excavate & Place Utility Conduit

Pedestrian/building access will be maintained.

Broadway between W. 45th St. & W. 46th St.

Grade & Place Base Concrete; Complete Pavers Between Trench Drain & Building

Pedestrian/building access will be maintained.

Duffy Square (west side)

Place Granite Pavers

Pedestrian/building access will be maintained.

Broadway between W. 46th St. & W. 47th St.

Seal Concrete Pavers

Pedestrian/building access will be maintained.


Night work, Monday-Friday, 10 pm-7 am

LOCATION

WORK

IMPACT

7th Ave. between W. 42nd St. & W. 43rd St.

Excavate & Place 12" Conduit

Pedestrian/building access will be maintained. Two southbound lanes of vehicular traffic will be closed at this location.

W. 44th St. & Broadway

Utility Conduit Installation; Backfill Utility Manhole Ducts

Pedestrian/building access will be maintained.

Broadway & W. 45th St. (north east corner) 

Install Additional Utility Conduit

Pedestrian/building access will be maintained.


**NOTE: Due to unforeseen conditions it may become necessary to change some scheduled work locations and operations.